Construction
Middle East
Defects during the project life
cycle: FIDIC and UAE law
By Alison Eslick and Roberta Wertman, Senior Associates, Reed Smith LLP
. . Defects during the project life cycle:
FIDIC and UAE law
Defects affect construction projects throughout their life-cycle – from design
to construction to use. UAE law and the FIDIC Red Book, the most common
form of construction contract adopted in the UAE, have numerous provisions
to address defects. Whilst the contractual and legal implications of defects
usually require intense investigation and are necessarily fact-specific,
Reed Smith’s UAE construction team presented the following hypothetical
case study at a recent discussion forum to illustrate some of those
implications. The analysis that follows the case study captures that discussion.
Case Study
In 2005, Big Developments entered into a construction contract (FIDIC Red-Book 1999) with Trusted Contracting
for delivery of “the biggest hospital in the world” to be owned and operated by Big Developments in Dubai.
The
project was a low rise development but featured a tall residential tower. The tower would be partially used for
accommodating hospital staff, but many units would also be sold to third party purchasers.
Big Developments entered into a separate contract with the consultant, Bling Buildings, for the design of the
project and supervision of the construction works.
There was intense pressure to deliver the project in time for the Dubai Healthcare Expo in 2008. The
construction went smoothly except for one major complication towards the end of the project that infuriated Big
Developments – Trusted Contracting installed a fire sprinkler system in the hospital building which was not
compliant with the Civil Defence Regulations.
This was discovered during a Civil Defence inspection and the
sprinklers had to be removed and replaced in the entire building, which jeopardised the completion date.
The project was miraculously completed on time and handed over in 2008.
A few years later things started to go wrong:
1 In 2009 residents of the tower complained to Big Developments that water was leaking through their ceilings.
It appeared to be coming from bathrooms in the floor above.
2 In 2010 a thick fungus was discovered growing in a gap between the interior and exterior walls of the entire
hospital. Big Developments was undergoing a corporate restructure and did not have time to take any
actions. The hospital had central air-conditioning but sometimes patients opened the windows because they
wanted fresh air.
By 2011, the fungus was out of control, producing a foul odour and was clearly visible. All
the walls in the hospital were affected.
3 In 2014, Big Developments sold the project to Better Developments who engaged So-So Contracting to
perform a major upgrade of the cardiology wing which looked dated. The original concrete slab had a few
small cracks but a new layer was placed over it.
Less than a year after the upgrade, much larger cracks
appeared in the floor.
Defects during the project life cycle: FIDIC and UAE law Reed Smith LLP 01
. What is a defect?
It seems obvious enough, but there is no universal or
simple definition of what a defect is. Most standard
form contracts, such as the FIDIC Red Book, do not
actually define the term ‘defect’. It is perhaps easier to
start with what a defect isn’t, and work backwards. The
following principles are a useful starting point:
walls was not an abnormal design feature because
buildings need to breathe.
•
The defect might have come from poor
workmanship, such as failure to properly seal the
cavity.
Unsupervised, unskilled labour may have led
to this issue.
•
•
“Nothing built is ever perfect; and the law does not
require perfection”
•
“Nothing built lasts forever; failure is an expected
result”
Involving facilities management specialists at the
design stage can contribute to a stronger design
and avoid future problems arising. There is a
growing awareness in Dubai of this preventative
step.
•
A defect is not fair wear and tear, which is caused
by normal ageing of a building.
Preventing and addressing defects: before
and during the construction period
•
A defect is not a problem caused solely by poor
maintenance or lack of maintenance (though these
could exacerbate a defect).
Defects can be in the design (where a design does not
meet standards of care or does not comply with
building regulations) or in the construction (where
work is not executed according to specifications or
does not meet acceptable standards of workmanship)
or where materials and equipment are not fit for
purpose.
There is an important distinction between a defect and
the manifestation of a defect (although both are
problems) – not all manifestations of a problem are the
result of a defect (e.g. a crack might be a symptom of a
bad design or poor workmanship but in some
circumstances, it may be fair wear and tear).
For completeness, the term ‘defect’ is not defined in
the UAE Civil Code or FIDIC, although there are a
number of references to defects throughout the Code
and the contract form, as well as references to the
standards of work expected.
It is worth noting that
under Article 880 of the UAE Civil Code, contractors are
obliged to construct a building that is free from total or
partial collapse and defects threatening its stability and
safety for 10 years after delivery of the works.
Turning to the case study (in which a number of
hypothetical companies will be referred to) there is
thick fungus appearing inside the hospital walls two
years after handover. It is a problem, but is it a defect?
•
Mould is a common problem in the UAE due to the
hot climate. Serious health issues can arise.
•
Mould is usually the manifestation of a design or
workmanship defect (or combination of both), but
can sometimes be purely the result of poor
maintenance, including incorrect use of, or poorly
functioning, air-conditioning units.
•
Designers in the forum leapt to the defence of
designer Bling Buildings, arguing that a cavity in the
Even before entering into the contract, a rigorous
tender clarification process can help to identify defects
or gaps in the design.
This process should give
employers an incentive to ensure that the design is
sufficiently developed for meaningful review at the
tender stage.
The FIDIC Red Book contains a number of provisions
that should have helped Big Developments avoid or
address defects during construction. Clause 7 provides
the employer and/or the engineer the right to:
•
Approve material samples before use
•
Inspect the manufacture of plant
•
Inspect production and manufacture of materials
•
Inspect work before it is covered up
•
Conduct tests
If the material, plant, or workmanship is defective or
otherwise not in accordance with the contract, the
engineer could have rejected Trusted Contracting’s
material, plant or workmanship and require Trusted
Contracting to remedy the defect at its own time and
cost.
When the inspection revealed that the fire sprinklers
were not in accordance with the contract, Trusted
Contracting might have argued that Big Developments
should bear the time and cost consequences of
replacement, including acceleration, since Big
Development’s engineer would have had multiple
opportunities to object to the fire sprinklers and
instead approved them.
While this is a common argument, absent special
circumstances it generally fails. Sub-Clause 4.1
provides that Trusted Contracting’s primary obligation
is “to execute and complete the works in accordance
with the contract…” The engineer’s sign-offs are of little
help.
Under Sub-Clause 3.1, the engineer does not
have authority to relieve Trusted Contracting of its
contractual obligations.
02 Reed Smith LLP Defects during the project life cycle: FIDIC and UAE law
. Defects liability period (DLP)
Trusted Contracting’s obligation to remedy defects
does not end with the taking over of the works by Big
Developments. Clause 11 of the FIDIC Red Book
provides for a period after taking over, during which
Big Developments may notify Trusted Contracting of
defects and require that Trusted Contracting rectify
them. Usually this period is one year, but it sometimes
is extended to two years.
Going back to the case study, Big Developments
should notify Trusted Contracting that there is water
leaking from the bathrooms above and require
rectification. If Trusted Contracting does not repair the
defects, Big Developments would be expected to carry
out the work and charge the costs against the
retention.
Trusted Contracting may inspect the leaks and
determine that, in fact, there isn’t a material or
workmanship defect, but rather there is a design
defect.
In that case, Trusted Contracting may refuse to
do the work without additional compensation.
Contractual liability for defects under UAE
law
Under UAE law, Big Developments could bring a
breach of contract claim against Trusted Contracting
for latent defects that are discovered after the expiry of
the DLP.
order to recover compensation from them. That said,
‘strict’ does not mean ‘absolute’ liability. The contractor
and architect may each defend themselves against a
claim for decennial liability by proving that the collapse
or defect arose from an ‘extraneous cause’.
For
example, the contractor might show that the fault was
with the design or the architect might show that the
fault was with the contractor. Perhaps the fault came
from a third party. In the extreme, imagine that a crane
falls on a building and the building collapses.
The crane
falling is an extraneous cause of the collapse, not a
cause from the design or construction. The same logic
can be applied to less extreme circumstances.
The application of decennial liability provisions under
the UAE Civil Code is complicated in cases of major
renovations and multiple owners, as contemplated by
the case study. When the hospital project is sold by Big
Developments to Better Developments in 2014, small
cracks have already formed in the original concrete
slab of the cardiology wing, approximately six years
after handover and within the 10-year decennial
liability period.
So-So Contracting performs a
renovation of the floor, concreting over the cracks, and
larger cracks appear less than a year after the
renovation. The following considerations arise:
•
Assuming the cracks threaten the stability and
safety of the building, what is the underlying source
of the defect? The rework by So-So Contracting? Or
the original work by Trusted Contracting? Or the
original design by Bling Buildings? Ultimately, this is
a factual question that would come down to expert
evidence. There may be multiple causes, including
major defects in the original work and design, as
well as the rework, which together have caused the
building to be structurally unsound and unsafe.
•
If the rework is extensive, Trusted Contracting and
Bling Buildings would probably have an argument
that there was an intervening, extraneous cause (i.e.
the rework by So-So Contracting) and that any chain
of causation between an original defect (if it was a
cause) and the loss suffered, has been broken.
Although decennial liability is strict, the UAE courts
have recognised some defences to decennial
liability, including force majeure or extraneous
causes, such as the actions of a third party after
handover.
Arguably, a major renovation by a third
party could be viewed as an external or intervening
cause.
•
Assuming the structural defect is isolated to the
rework, Better Developments could sue in
decennial liability for structural defects in the
rework because Better Developments takes on a
developer role in respect of the renovation.
However, if the structural defect stems from the
original work by Trusted Contracting or the original
design by Bling Buildings, Better Developments (as
the new owner/end user) would have difficulty in
Article 95 of the Commercial Transaction Law provides
for a 10-year statute of limitations for bringing breach
of contract claims that runs from the date when the
obligations are due.
Therefore, Big Developments may be able to bring a
claim against Trusted Contracting if the fungus
manifests after the DLP and if Big Developments could
not have discovered the defect giving rise to the fungus
during the DLP.
Decennial liability
Articles 880 to 883 of the UAE Civil Code govern
‘decennial liability’. These provisions provide rights to
employers/developers against contractors and
supervising engineers/architects in the case of total or
partial collapse of a building, or where a defect
threatens the stability and safety of the building. If the
architect does not supervise the execution, the
architect is held liable only for defects in the design.
Contractors and supervising architects are held jointly
liable for 10 years and it is not permitted to contract
out of decennial liability.
Once a building has collapsed
or a defect has been discovered, the employer has
three years in which to bring a claim.
Decennial liability is a strict liability standard, which
means that an employer is not required to show any
wrongdoing by either the contractor or the architect in
Defects during the project life cycle: FIDIC and UAE law Reed Smith LLP 03
. making a direct claim against Trusted Contracting
and/or Bling Buildings because, on the face of
Article 880, this provision is not open to any third
party (i.e. a new owner/end user) who has no
contractual relationship with the contractor or
supervising engineer/architect to sue in decennial
liability. The protection is for the
employer/developer only (not the end user, even if
this is another developer).
•
•
As an end user, Better Developments is not without
legal recourse against Trusted Contracting and/or
Bling Buildings. Better Developments could sue
them in tort for negligent design/construction.
There is also an argument that decennial liability
rights run with the property pursuant to Article 251
of the Civil Code.
This is untested but there could be
a public policy argument that the intent of decennial
liability is to protect against the effect of structurally
unsound buildings. Therefore, Article 251 should be
applied to allow decennial liability rights under
Article 880 to run with the property.
Better Developments would be wise to mitigate
against the risk of purchasing a structurally
unsound building under its sale and purchase
agreement (SPA) with Big Developments. Better
Developments should insist upon a strict warranty
guaranteeing the structural stability and safety of
the building for at least 10 years.
This will create a
chain of liability so that Better developments can
sue Big Developments under warranties in the SPA
and Big Developments can sue Trusted Contracting
and/or Bling Buildings under statutory decennial
liability.
•
Would Big Developments lose its rights to make a
claim in decennial liability by selling the hospital to
Better Developments before the 10-year statutory
decennial liability period expires? Article 880 does
not address this scenario. It was drafted in the
eighties well before the UAE boom in construction
and major projects, and did not contemplate
multiple sales of a development within 10 years
after delivery of the works. However, it is not
possible to contract out of Article 880 and Big
Developments would have a good argument that
the sale could not deprive its rights under
Article 880.
•
a number of years.
If a developer enlists an
engineer who confirms a structural defect, the
three-year period for bringing a claim will likely run
from the time of receiving that report.
Strata Law
In Dubai, Law 27 of 2007, Law of Ownership of Joint
Properties (Condominiums), was intended to protect
owners of jointly owned property from the
consequences of defects.
Under the law, the developer remains liable to the unit
owners or owner association for repairing or correcting
any defects of the structural parts of the joint property
for 10 years after the date of the completion certificate.
Likewise, the developer remains liable for repairing or
replacing defective installations, such as mechanical
and electrical works, for one year.
In practice, we expect that pursuing rights under this
law would be difficult although the Dubai Land
Department has been issuing guidelines and
regulations over time to make the law more effective.
Owners associations, however, are not generally
formed and the costs for individual unit owners in
pursuing claims against developers would be expected
to be prohibitive.
In the case study, the third party purchasers could
consider action against Big Developments in 2009 if
the water problems arose from the defects covered by
the Dubai law and Big Developments did not action to
correct them.
Reed Smith UAE construction discussion
series
Both Big Developments and Better Developments
should be mindful that a decennial liability claim
must be made within three years of discovery of the
defect. The UAE courts have indicated that the
discovery of the defect is considered the point at
which there is actual knowledge of the occurrence
of the damage, and certainty with regard to it. This
is a matter of fact within the discretion of the trial
court.
A developer will run a risk if they turn a blind
eye to the cracks, or bury their head in sand and
refuse to enquire about the cause of the cracks for
Reed Smith’s discussion series consists of small,
informal group sessions with lively discussion and
debate. Participation is by invitation only. For more
information about Reed Smith’s discussion series or its
construction team, please contact any of the
individuals listed under Key Contacts.
04 Reed Smith LLP Defects during the project life cycle: FIDIC and UAE law
.
Key Contacts
Paul Taylor
Partner
Björn Gehle
Partner
Dubai
+971 (0)4 709 6322
ptaylor@reedsmith.com
Dubai
+971 (0)4 703 6312
bgehle@reedsmith.com
Simon Harvey
Partner
Alison Eslick
Senior Associate
Dubai
+971 (0)4 709 6311
sharvey@reedsmith.com
Dubai
+971 (0)4 709 6357
aeslick@reedsmith.com
Kristine Kalnina
Senior Associate
Mireille Taok
Senior Associate
Dubai
+971 (0)4 79 6345
kkalnina@reedsmith.com
Abu Dhabi
+971 (0)2 418 5759
mtaok@reedsmith.com
Roberta Wertman
Senior Associate
Abu Dhabi
+971 (0)2 418 5785
rwertman@reedsmith.com
Defects during the project life cycle: FIDIC and UAE law Reed Smith LLP 05
. Reed Smith is a global
relationship law firm with more
than 1,800 lawyers in 26 offices
throughout Europe, the Middle
East, Asia and the United States.
Founded in 1877, the firm represents leading international businesses, from FTSE 100
corporations to mid-market and emerging enterprises. Its lawyers provide litigation and other
dispute-resolution services in multi-jurisdictional and high-stake matters, deliver regulatory
counsel, and execute the full range of strategic domestic and cross-border transactions.
Reed Smith is a preeminent advisor to industries including financial services, life sciences,
health care, advertising, entertainment and media, shipping and transport, energy and
natural resources, real estate, manufacturing and technology, and education.
This document is not intended to provide legal advice to be used in a specific fact situation; the contents are for informational purposes only.
“Reed Smith” refers to Reed Smith LLP and related entities. © Reed Smith LLP 2016
ABU DHABI
ATHENS
BEIJING
CENTURY CITY
CHICAGO
DUBAI
FRANKFURT
HONG KONG
HOUSTON
KAZAKHSTAN
LONDON
LOS ANGELES
MUNICH
NEW YORK
PARIS
PHILADELPHIA
PITTSBURGH
PRINCETON
RICHMOND
SAN FRANCISCO
SHANGHAI
SILICON VALLEY
SINGAPORE
TYSONS
WASHINGTON, D.C.
WILMINGTON
reedsmith.com
06 Reed Smith LLP Defects during the project life cycle: FIDIC and UAE law
.