APRIL 2016 n NO. 4
Maritime
The Well Control Final Rule Is Here, Finally
Action Item: The recently published Well Control Rule will
require significant changes to Blow-Out Preventer (“BOP”)
systems and well operations. Stakeholders in offshore oil and
gas operations should carefully evaluate the new measures,
review safety procedures, and develop plans to come
into compliance within the time frames mandated by the
regulations.
New Developments
The Department of Interior’s Bureau of Safety and Environmental
Enforcement (“BSEE”) released its Final Rule on Well Control
Regulations (the “Final Rule”) on April 14, 2016. The Final Rule
adopts new standards for safety and well operations that will be
required for owners and operators of offshore wells and facilities.
The Final Rule has yet to be published in the Federal Register, but
will be shortly, and it will go into effect 90 days after publication,
with some provisions being implemented at later dates.
Background
Following the Deepwater Horizon incident, the former Bureau
of Offshore Energy Management, Regulation, and Enforcement
(“BOEMRE”) (now reorganized into BSEE and Bureau of Ocean
Energy Management or BOEM) published an Interim Final
Rule (“IFR”) titled “Increased Safety Measures for Energy
Development on the Outer Continental Shelf” on October 14,
2010.
Highlighting the five-year anniversary of the Deepwater
Horizon incident, the Bureau of Safety and Environmental
Enforcement (“BSEE”) issued its Proposed Rule on April 17,
2015, regarding BOPs and Well Control, and the Department of
the Interior published a joint BSEE/BOEM notice describing the
reforms the agencies have implemented since the 2010 incident.
(See Proposed Rule and Joint Notice.) We have covered these
developments in previous advisories, most notably our April
2015 advisory titled “BSEE and DOI Take Action on Five-Year
Anniversary of Deepwater Horizon.”(See http://www.blankrome.
com/index.cfm?contentID=37&itemID=3571.)
BSEE’s Final Rule on Well Control
BSEE’s stated goal in implementing the Final Rule was to “ensure
safe and responsible offshore oil and gas development.” To this
end, the Final Rule sought to incorporate lessons learned from
the Deepwater Horizon incident, the subsequent investigations
of the incident, and the hundreds of comments received by
BSEE. Most requirements become effective three months from
the publication of the Final Rule, while some requirements have
extended timeframes for compliance.
© 2016, Blank Rome LLP. All rights reserved.
Please contact Blank Rome for permission to reprint. Notice: The purpose of this update is to identify select developments that may be of interest
to readers. The information contained herein is abridged and summarized from various sources, the accuracy and completeness of which cannot be assured.
This update should not be
construed as legal advice or opinion, and is not a substitute for the advice of counsel.
. Maritime n Page 2
The Final Rule amends standards, controls, and maintenance
requirements for BOPs, requires real-time monitoring capability
for some drilling activities, and modifies requirements for well
control and decommissioning.
The Final Rule, among other things, will accomplish the
following:
i
ncorporates new industry standards for baseline
requirements for the design, manufacture, repair, and
maintenance of BOPs;
andates more controls over the maintenance, inspection,
m
and repair of BOPs;
equires the use of deepwater and surface BOPs with
r
double shear rams, designed to include technology that
allows drill pipe centering during shearing operations;
equires more vigorous third-party verification and
r
certification of BOP equipment;
equires real-time monitoring of deepwater and high
r
temperature and high-pressure drilling activities, as well as
shallow water operations in high-risk cases;
stablishes regulatory criteria for testing subsea well
e
containment equipment based on an existing Notice to
Lessees on well containment;
increases reporting requirements of failure data;
dopts criteria for safe drilling margins, according to
a
recommendations of investigations of the Deepwater
Horizon incident;
specifies requirements for remote operating vehicle use;
andates the testing frequency of BOPs used on workover
m
and decommissioning operations the same as drilling
operations; and
i
ncorporates guidance from several Notices to Lessees and
Operators.
Industry and Environmental Response
There have been concerns about the rulemaking process
and the requirements in the Final Rule. In particular, some
industry segments expressed concerns about the unintended
consequences of uniform regulations for diverse operations.
Some of these concerns were addressed in the Final Rule. For
example, the “safe drilling margin” established in the Final Rule
provides more flexibility to operators than what was in the
proposed rule. Industry also expressed concerns regarding the
implementation schedule.
BSEE claims to have addressed this
concern by delaying implementation of certain provisions.
However, one area of industry concern that was not addressed
by BSEE was regarding the rulemaking process. In particular, the
National Ocean Industries Association (“NOIA”) noted that the
Final Rule was the culmination of a flawed rulemaking process
due in part to BSEE’s refusal to extend the time for comments,
including time to consider new economic studies, and pull back
and rewrite portions of the rule.
The American Petroleum Institute, NOIA, and other industry
groups have stated that they support the Final Rule’s attempt
to build upon the progress made by the industry on safety.
However, other groups noted that there were less restrictive
means to accomplish BSEE’s goals.
Environmental groups have also shared a diversity of opinions.
Some groups have signaled that the Final Rule is an improvement
over the status quo. However, they note their belief that the
Final Rule does not go far enough in mandating safety and
environmental requirements.
Conclusions
Now that the Final Rule has been published, and regardless
of whether a particular entity or organization has supported
this rulemaking, it is time for owners and operators of offshore
facilities, contractors, and other stakeholders to do a deepdive, so to speak, to fully examine the Final Rule and to take the
necessary time to understand and develop a plan to come into
compliance within the mandated timeframes.
Challenges to the
Final Rule are already beginning to take shape. For example,
it was announced two days after the Final Rule’s release that
Senator David Vitter (R-La.) has proposed an amendment to the
Energy Bill, which has been stalled for a while but is now moving,
that would require BSEE to conduct a review of the Final Rule’s
economic impact on small businesses. Time will tell whether
some companies will decide to challenge certain provisions of
the Final Rule or take other action to seek alternatives or relief.
— © 2016 BLANK ROME LLP
For additional information, please contact:
Jeanne M.
Grasso
202.772.5927 | Grasso@BlankRome.com
Jonathan K. Waldron
202.772.5964 | Waldron@BlankRome.com
Stefanos N. Roulakis
202.772.5958 | SRoulakis@BlankRome.com
.
.